The New SLC Airport Phase II Plans Advance
"It is a dark cloud indeed that doesn't have a silver lining in it somewhere," Bill Wyatt noted in a recent media interview about the impact COVID-19 is having on SLC Airport. In light of fewer passenger traffic the SLC team has been exploring options to determine the best way to move forward with Phase II of The New SLC Redevelopment Program.
"We won't have to use any part of the old airport after October of this year," Bill said. "We will tear them all down at once." Noting that with fewer passengers the additional gates are no longer needed. "This plan eliminates a lot of the complexity and allows us to save a lot of money," he continued.
The condensed timeline-completion by December 2024, rather than early 2027-will shorten Phase II by two years and is expected to save up to $300 million. Phase II includes building out the east side of Concourse A.
|